To whom is the special inspector generally required to send their final report?

  1. The project manager only

  2. The contractor

  3. The building official and design professional in responsible charge

  4. The city council

The correct answer is: The building official and design professional in responsible charge

In construction projects, the role of a special inspector is critical in ensuring that all work complies with relevant codes, standards, and project specifications. The final report from a special inspector typically includes findings, observations, and any issues related to compliance during the inspection process. The correct choice highlights that the final report is generally required to be sent to both the building official and the design professional in responsible charge. This is essential because the building official needs to maintain oversight of the project to ensure that it's being constructed according to applicable regulations and standards. The design professional, typically an engineer or architect, is responsible for the overall design and specifications of the project and needs to be informed about any compliance issues or notable findings that could impact the design's integrity or functionality. This dual reporting requirement is in alignment with construction practices where collaboration and communication between inspectors, building officials, and design professionals are vital for project success and safety.