Upon arriving on-site, whom should the special inspector notify?

  1. The building official

  2. The design professional

  3. The contractor

  4. The project owner

The correct answer is: The contractor

The special inspector's role is to provide oversight and ensure that construction complies with the approved plans and specifications, as well as applicable building codes. When arriving on-site, it is crucial for the special inspector to notify the contractor because the contractor is responsible for the actual work and coordination on-site. By notifying the contractor, the special inspector establishes communication to ensure that the contractor is aware of the inspector's presence and can address any compliance issues that may arise during the inspection process. The contractor can then make necessary adjustments, facilitate required observations, and ensure that all work aligns with the established standards. Effective communication between the special inspector and the contractor helps maintain the integrity of the project and ensures that all inspections are conducted timely, enabling swift resolution of any concerns that might otherwise impact construction progress.