Prepare for the ICC General Requirements Test. Use flashcards and multiple-choice questions with detailed hints and explanations. Ace your exam with confidence!

Practice this question and more.


Which items must be included in an inspection report by the special inspector?

  1. Frequency of inspection and building codes

  2. Checklist of materials used

  3. A non-conforming item, inspection location, and inspection type

  4. Cost estimates and contractor performance reviews

The correct answer is: A non-conforming item, inspection location, and inspection type

The correct choice emphasizes the necessity for the inspection report to document specific observations and technical findings related to the construction process. Including a non-conforming item, the inspection location, and the inspection type provides a comprehensive overview of the quality and compliance of the work being inspected. A non-conforming item highlights any deviations from the approved plans or applicable codes, ensuring accountability and clarity on what issues need to be addressed. Identifying the inspection location adds context to the findings, allowing for easy reference during follow-ups or corrections. Specifying the inspection type demonstrates the nature of the assessment conducted, whether it was a visual inspection, testing of materials, or a review of construction practices. Collectively, these elements ensure that all relevant aspects of the inspection are recorded, facilitating communication between the inspector, contractors, and stakeholders involved. In contrast, while aspects like frequency of inspection and building codes may inform the process, they do not specifically pertain to individual inspection reports. A checklist of materials used might be useful but is not mandated for every inspection report. Cost estimates and contractor performance reviews are generally outside the purview of what is included in inspection reports by special inspectors, which focus more specifically on compliance and code adherence rather than financial metrics or contractor evaluations.