Which party typically conducts a pre-construction meeting?

  1. The contractor

  2. The building official

  3. The registered design professional (RDP)

  4. The owner

The correct answer is: The registered design professional (RDP)

The registered design professional (RDP) is typically responsible for conducting a pre-construction meeting. This role is crucial because the RDP is often the individual who has developed the construction documents and understands the project's design intent. During the pre-construction meeting, the RDP coordinates with key stakeholders, including the contractor, owner, and potentially building officials, to discuss project specifications, timelines, safety protocols, and any other essential details that need to be clarified before construction begins. This meeting serves as an opportunity to align everyone's understanding of the project, ensuring that all parties are aware of their roles and responsibilities. By leading this meeting, the RDP can facilitate a collaborative environment, addressing any concerns and reinforcing communication channels that will be critical throughout the project's duration. While contractors, building officials, and owners all play important roles in the construction process, the RDP's expertise in the design and understanding of code requirements positions them appropriately to lead the discussion at this initial stage.