Prepare for the ICC General Requirements Test. Use flashcards and multiple-choice questions with detailed hints and explanations. Ace your exam with confidence!

Practice this question and more.


Who is responsible for approving the special inspection program?

  1. The special inspector

  2. The contractor

  3. The design professional

  4. The building official

The correct answer is: The building official

The responsibility for approving the special inspection program lies with the building official. This role is critical because the building official ensures that all aspects of the construction comply with relevant building codes and regulations. The special inspection program is established to verify that specific construction activities meet the required standards, particularly for complex or critical elements of a project. The building official assesses the proposed inspection program to ensure it aligns with the established codes and requirements set forth by the jurisdiction. This involves reviewing the qualifications of the special inspectors, the types of inspections required, and the associated procedures to be followed during construction. Ultimately, the building official's approval safeguards public safety and ensures the integrity of the construction process. While other roles, such as the special inspector and the design professional, have important functions in the inspection process, their involvement is more about executing or recommending aspects of the inspection rather than having the authority to approve the entire program. The contractor also plays a vital role in facilitating the inspection process but does not hold the responsibility for program approval.